This is an example of a relatively small project, delivered economically
and ahead of schedule through Syska Hennessy's remediation contract
with the USACE. Total construction contract value was $145,000
including a new concrete pad, extension of an existing concrete
loading dock, installation of a new 150W outdoor diesel generator
unit, modification sand tie-in to the existing electrical distribution
system serving data processing loads. Syska Hennessy conducted
a site survey to verify the required generator capacity and the
existing electrical system serving the computer facility, and to
establish a location for the new generator. Next, a detailed work
plan was done, including required drawings, specifications and
narrative to document the quality, scope and cost of the project.
Syska Hennessy's services also included complete installation,
testing and commissioning of the generator system, including supervision
of cut-over to serve the data processing equipment. In spite of
the unusually severe winter, our team replaced a 150W outdoor generator
on time and within budget by accelerating the construction schedule
to achieve installation during windows of fair weather.
|
 |